Report: River Bend data center Phase II plans pushed back again

10 minutes 56 seconds ago Thursday, November 05 2026 Nov 5, 2026 November 05, 2026 9:43 AM November 05, 2026 in News
Source: The Advocate

ST. FRANCISVILLE — Phase II plans for the Hut 8 data center coming to West Feliciana Parish have been pushed back again over worries about its proximity to a neighborhood, according to a report by The Advocate. 

Original plans placed the Phase II facility less than a mile from houses in the Star Hill neighborhood of St. Francisville, the newspaper reported. 

At an early-November West Feliciana Planning and Zoning Commission meeting, commissioners reportedly decided to rework the plans to possibly move the Phase II site closer to the Phase I site along La. 964. 

Hut 8 officials were not at that meeting, The Advocate reported, and the company has until Dec. 1 to reapply for zoning changes. 